I drive up/down West Bay Road four times a day from home to work and for at least nine months now, there has been roadworks of various degrees on the half mile stretch from the mini-roundabout opposite Blue Cilantro to the traffic lights next to the Rubis. I’m at a loss to explain why the same portions of the road are being dug up on a daily basis and who is actually doing the digging (presumably it’s one of the cable/fibre-optic companies). Also, what approvals do companies need to dig up the roads, do they have to give a timeframe and do they have to fix the road back to the same standard as it was previously? The reason I ask is the quality of the road surface has deteriorated since the roadworks and the markings on the road have not been adequately replaced (e.g. the red block on the road to warn of the pedestrian crossing). 


Auntie’s answer: Dealing with roadworks is one of those occurrences that I feel safe to say no one likes, especially if the same spot seems to be in a constant state of upheaval. To address your concerns, I took your questions to the National Roads Authority (NRA).

An NRA official very patiently answered everything I threw at him – and I ask a lot of follow-up questions. Let’s start with the approvals process. Permission is granted for roadwork after the utility company or sub-contractor complies with the NRA trench-application procedures. In addition, the applicant can excavate more than once within the 200ft approved permit limit.

Importantly, that approval is contingent on whoever is doing the trenching being responsible for restoring the affected area back to or better than its original condition.

This area of accountability falls within the road reserve covered in the application. For those who care to know, the road reserve includes the paved area as well as the shoulders. So for a standard subdivision road this would translate to a 30ft road reserve having 24ft in pavement (12ft lanes) with 3ft shoulders on either side, though that could very depending on the road in question.

The companies that do the digging also have to comply with a timeframe, as you asked. The NRA official explained that this timeframe may vary from project to project. “Normally it’s three months to a year from the date the permit has been approved,” he said, adding an explanation for the area you asked about: “In this case that area was excavated by more than one utility company and it will take longer to complete the total upgrades.”

One final point, the NRA does not take kindly to companies that are slow to reinstate the road after completing whatever trenching they were doing: “And if isn’t repaired in a timely matter, the applicant may have other future permits deferred until compliance is met.”